Proposal

Title Strengthening the monitoring Capacity of Petroleum Downstream Operations Regulatory Directorate
Regional Br. / Line Min. Ministry of Water,Irrigation and Energy
Sector Water and Energy
Benefeciary
Partner(s)
Start Date - End Date July 01, 2014 - December 31, 2015
Total Budget USD 635,000
Requested Facility Budget USD 635,000
Approved Budget USD 635,000 $
Region Addis Ababa
Zone
Woreda
Kebele
city
Environmental and Social Safeguard
Environmental and Social Safeguard Category
Executive Summary This project aims in replacing 42 diesel driven water pumping system with renewable energy pumping systems and aims in Supplying and Installation of 42 solar water supply pumping units in Amhara, Tigray, Oromia & SNNP Regions with a total project budget of USD 2,713,874.00
Created On 2015-10-19
Created By Getnet Fetene

Physical and Financial Progress Report for this Project

There are no Progress report for this Project!